Saturday, 31 October 2009

North Hoyle Met Mast Decommissioning - 2009

Lead Engineer for demolition of a piled concrete dolphin and met mast for the North Hoyle Offshore Wind Farm.

Copyright (c) Nick Wordsworth 2014

Works were conducted from the Fugro Seacore vessel Excalibur. The met mast was removed in two sections and then the concrete section was held in position while it was cut free form the piles. An internal pile cutting tool was used to cut each pile at approximately 2m below seabed.


Video Copyright (c) Neil Evans 2009

Employed by: Noble Denton. Client: RWE npower. Duration: 6 mths.