Westermost Rough Foundations Installation 2012-2014

Installation Manager for 35 monopile foundations for the 210MW project using new Siemens 6MW turbines

Copyright (c) Nick Wordsworth 2014

Managing the installation process for WTG foundations from preliminary planning analysis through to completion on site, I was responsible for ensuring technical quality and safety of all processes. This included the load out, 5 foundations at a time, from a quayside within the fabrication area - see below video.





Copyright (c) Nick Wordsworth 2014
Implementing a campaign of proactive monitoring, reporting and interrogation of Contractor schedule, progress and subcontracted activities, I was able to ensure  that the key deliverables were procured, fabricated and delivered on time.


Copyright (c) Nick Wordsworth 2014

Throughout the project, I undertook internal audits and reviews within project organisation to maintain quality of technical documentation and plans. This included an extensive HAZID and subsequent risk avoidance campaign, altering the permanent works design to improve manual handling during construction and thereby minimise offshore working time.


Copyright (c) Nick Wordsworth 2014

The main installation vessel works started in middle February 2014 and were complete by end of May 2014. Secondary works completed early June 2014, 3 weeks ahead of schedule. All documentation reviewed and fully transferred to project by end of June.

Works carried out by Geosea from vessel HGO Innovation.

Employed by: DONG Energy. Client: Westermost Rough Ltd. Duration: 29 months.